Get the power flowing

Meter installation and energization process

Getting a Site Identification number (Site ID) is a common first step to setting up a new electrical connection or upgrading an existing service. Learn the steps involved to get a new or temporary electrical service in your home or business. 


20240130-MeterExchange-026

Step 1: Plan your work or project

Step 2: Obtain a Permit

Step 3: Get a Site ID​

Step 4: Choose your Retailer

Step 5: Is your site ready for energization?

Step 6: Request Site Energization 

Step 7: We're on our way 

Current Transformer (CT) metered site

Current-Transformer (CT) Metered Site

CT request form:

CT site readiness:

Installation will be scheduled during regular working hours (M-F; 8AM - 4 PM) unless otherwise requested. After-hours work can be requested and is subject to availability. Please note, an additional after-hours fee will apply. Request here.

Contact for CT Meter Site:

403-514-3780 or email RMC@enmax.com

Important resources

Location-map icon

System capacity maps

Learn about the location and capacity available within the ENMAX Power distribution service territory.

Access system capacity maps
Editor Choice.png

Standards & Regulations

Learn more about ENMAX Power Standards & Regulations.

Learn more
Warning Icon.svg

Safety guidelines

Learn more about electrical and project safety.

Review safety guidelines